The St. Paul the Apostle Commons addition is quickly approaching the finish line! Over the past couple of weeks the main areas have seen near-completion of electrical installations, drop ceilings completed, the final touches on the roof, and, just a few days ago, carpet being laid. Early this coming week we are scheduled to have the fire alarm system connected to the main building, which will allow for the removal of the temporary walls separating old from new, which will then allow the refinishing of the connection between the two. Overall we expect that by the second week of March all trades are complete (not including the restoration of the outside) and we are focusing on punch list items so we can get moved in!
We are so blessed, through the generosity of the whole SPA community, to have the opportunity to get this much-needed project done. It will serve such a great purpose to both parish programming and school operations in allowing us all to continue and expand our mission of faith.